Blacklisting order number: No. 1 Series of 2022

Name of Blacklisted Entity Solid M Construction
Name of Individual/s Martin Junboy C. Tan
Address 534 Corcino Compound, Brgy. Airport Village, Catarman, Northern Samar
PhilGEPS Nos: 2010-62530
Blacklisting order number: No. 1 Series of 2022
Date of Blacklisting Order 2022-09-07
Name of the project Construction of Diversion Dam and Irrigation Canals of Hagbay Irrigation Project
Amount of contract 81,418,066.75
Project location Las Navas, Northern Samar
Offense committed Does not actually have on the the project site the minimum essential equipment listed on the Bid necessary to prosecute the Works in accordance with the approved work plan and equipment deployment schedule as required for the project; and Does not execute the Works in accordance with the contract persistently or flagrantly neglects to carry out its obligations under the contract.
Stage violation is committed Contract Implementation
Sanction imposed  
Duration 2022-09-07 to 2023-09-06
HOPE/Signatory Ruby C. Tuan, Jr.